Preparations
|
|
|
|
Controlled
Demolition Group first set about drilling 360 holes at the
50-foot elevation of the smaller stack. The holes were then
loaded with 150 pounds of 80% gelatin and covered with strips
of conveyor belting to contain debris from the initial blast.
While this was occurring, workers from Brown & Mason
began stacking large container bins three-high, eventually
building a 30 by 300-foot-long protective wall in front
of the adjacent active power station. This wall would prevent
debris generated by the stack's ground-slap from striking
the station's operating transformers. |
|
Preparing
the larger concrete stack proved far more arduous, as hand
drills and other cutting equipment had to be carried up
through the inside of the giant shaft to the 350-foot level.
Aside from the usual drilling and loading, workers used
blow-torches to pre-cut each of the four steel ducts, as
well as stairwells and various other items to insure that
the top half of the structure would separate quickly upon
detonation.
|
|
Explosives
engineer Holly Bennett carries a load of detonators
onto the blast site
|
|
|
|
|
Once
the high elevation was fully prepared, work began on the
stack's base, with over 200 holes being drilled in a wedge-shaped
pattern that extended 120 feet around and more than 30 feet
high. A total of 400 pounds of explosives were loaded into
the 725-foot stack, and like its shorter 350-foot counterpart,
conveyor belting was then placed over the charges to help
contain any initial blast debris. |
|
|
|