Preparations
  Controlled Demolition Group first set about drilling 360 holes at the 50-foot elevation of the smaller stack. The holes were then loaded with 150 pounds of 80% gelatin and covered with strips of conveyor belting to contain debris from the initial blast. While this was occurring, workers from Brown & Mason began stacking large container bins three-high, eventually building a 30 by 300-foot-long protective wall in front of the adjacent active power station. This wall would prevent debris generated by the stack's ground-slap from striking the station's operating transformers.
Preparing the larger concrete stack proved far more arduous, as hand drills and other cutting equipment had to be carried up through the inside of the giant shaft to the 350-foot level. Aside from the usual drilling and loading, workers used blow-torches to pre-cut each of the four steel ducts, as well as stairwells and various other items to insure that the top half of the structure would separate quickly upon detonation.
Explosives engineer Holly Bennett carries a load of detonators onto the blast site
  Once the high elevation was fully prepared, work began on the stack's base, with over 200 holes being drilled in a wedge-shaped pattern that extended 120 feet around and more than 30 feet high. A total of 400 pounds of explosives were loaded into the 725-foot stack, and like its shorter 350-foot counterpart, conveyor belting was then placed over the charges to help contain any initial blast debris.

CLICK ON A LINK BELOW TO CONTINUE

INTRODUCTION
DEVISING A PLAN
PREPARATIONS
BLAST DAY

Back to category list

  Enter your E-mail address below,
  and we'll keep you informed on site
  updates and future live events.